Posts Tagged ‘United Bank of India’

Diptimayee parida v United Bank of India

Monday, October 19th, 2009

zOFFICE OF THE DISTRICT CONSUMER DISPUTES REDRESSAL FORUM, JAGATSINGHPUR

PRESENT:-   SRI S.N.MISHRA,PRESIDENT.

A N D

SRI   B.C. SWAIN, MEMBERS.

MRS. M.M.RATH, MEMBERS.

Consumer Complaint No.79 of 2009

Date of Filing: -06.06.2009

Date of Judgment: -19.10.2009

Diptimayee parida

w/o-Manas kumar parida

vill-Arilo

Po-Sampur

Ps-Balikuda

Dist-Jagatsinghpur

……………………….complainant

Versus

1.     The Branch Manager

United Bank of India

Dihasahi Branch

At-Dihasahi(champahat)

Po-Dihasahi

Via-Tiran,Ps-Erasama

Dist-Jagatsinghpur

2.     General Manager

Dist-Industry Center

Jagatsinghpur

At/Po/Dist-Jagatsinghpur

………………………..Opp.parties

In short  the allegation of complainant is that being selected to avail facilities available to her under PMEGP 2008-2009 scheme  for running an automatic chuda mill her project stood approved as special women category by selection committee i.e. D.T.F. on  PMEGP as such vide letter 195 dtd.20.01.09 , the DIC, Jagatsinghpur intimated to the branch Manager,UBI,  Dihasahi branch to sponsor loan proposal within  period stipulated or to return the proposal in case  the loan proposal is not possible  with the reasons  for further action at it’s end. The branch Manager has not considered the matter for months together  despite repeated persuasion for which a legal notice  dtd. 05.03.09 got served on it but of no response. The  husband of the complainant said to have collected  information from DIC,Jagatsinghpur under RTI Act that  vide letter dtd.11.03.09 to DIC her proposal has been  returned on unreasonable grounds such as , the petitioners  is a house wife and studied up to class VII, in fact ,  she is plucked matriculate, having no technical  knowledge besides lacks sufficient homestead land  for construction of a shed. According to complainant her  father –in-law is in occupation of vast homestead land  and viable of scheme is potential as paradeep port is  only 35 kms. Away from her place besides good  communication made available to cuttack malgodown. It  is further alleged that arrogant belated report of O.P.  bank at the instance of inimical persons of complainant  has deprived her of availing facility hence she sustained mental agony financial loss as such seeked redressal within scope of this Act.

The General Manager , DIC, Jagatsinghpur (O.P. No.2) instead of filling written version has submitted a parawise comment which has no leg to stand hence not accepted for purpose of this proceeding. Ultimately O.P.No.2 is proceeded exparte due to non participation despite it’s knowledge of this proceeding.
The Branch Manager, UBI, Dihasahi Branch (O.P.No.1) submitted written version which speaks in short that this complaint has been undervalued being valued at Rs.50,000/- despite due knowledge of complainant  of it’s value at Rs.24,85,000/- as such this complaint is not to be entertained within meaning of this Act. It is contended by answering O.P.No.1 that complainant had nothing to do with such scheme forwarded by DIC (O.P.No.2) seeking opinion as to it’s viability besides such scheme on proper enquiry and consultation as found not viable and feasible  for production and marketing of 900 quintals of chuda and 500  quintals husk per month , vide letter annexed-1 has been returned  to DIC,Jagatsinghpur (O.P.No.2).  Disputing allegations alleged  in paragraph 1 to 4 it is stated that complainant being  an untrained person, besides due to want of huge  demand in local marked of such production this proposal has been returned to DIC to avoid risk to finance as such no deficiency in service is caused so as to be amiable within meaning of this Act.

Out of aforesaid pleadings of both parties it is evident to be a case of non sanction  of loan under PMEGP 2008-09 favoring complainant. Out of  letter dtd. 29.01.09 of DIC to bank it is further transpired that a scheme worth Rs.24,85,000/-  has been submitted before O.P.Bank for financial assistance to complainant. In said letter towards last portion  it is revealed to have been incorporated that the said proposal if  not sanctioned should be returned to DIC at an earliest for  further actions. The O.P.Bank in receipt of said proposal seems to have proceeded with the same and found non viable  of scheme and unsafe of the loan hence returned the proposal to DIC vide letter dtd. 11.03.09  stating the grounds there in.  therefore, the O.P.Bank can not be held to have  caused deficiency in service in any manner. On the contrary the DIC in receipt of the letter dtd. 11.03.09 seems  to have neither took any further steps to assist complainant  nor informed her about refusal of her loan by bank on the grounds stated therein. If DIC would have acted diligently definitely such a proceeding would have been avoided , as such, DIC is found to have caused  deficiency in service hence  accountable within  this act.  So DIC should find  out a way to fulfill the scheme of the complainant but not the O.P.Bank.

It has been rightly pointed out by the O.P. bank taking advantage of letter dtd. 29.08.09 of DIC that complainant has under valued her complaint to  attract the jurisdiction of this Forum. In stead letter the scheme  seems to have been valued at Rs.24,85,000/- but complainant has valued her complaint only at  Rs.50,000/- for the purpose jurisdiction and fees.  Such practice is not permissible within scope of this Act. That apart, the complainant  also failed to show with evidence that she has availed / hired the services of O.Ps. for consideration in any manner at any point of time.

Taking all these evidence available on record to active consideration we are not inclined to proceed with this complaint. However if the project of complainant according  DIC  is required to be  implemented , then DIC may proceeded on its way in the process of law prescribed under such scheme.

ORDER

In the result this complaint is dismissed on contest against O.P.Bank and exparte against DIC, Jagatsinghpur with aforesaid observation but without cost.

Serve a copy of this on DIC , Jagatsinghpur at the cost of the complainant for reference.

Pronounced in the open forum on this 19th day of October,2009.

Smt.M.M.Rath            B.C.Swain                     S.N.Mishra

MEMBER                  MEMBER                     PRESIDENT