DISTRICT CONSUMER DISPUTES REDRESSAL FORUM, NAYAGARH .
C.C. Case No. 15 of 2009
30th June , 2009 .
BEFORE :
Sri P. K. Pattanaik , President ,
Sri P. K. Mishra, Member
AND
Smt. Binodini Devi , Member .
Name of the Parties .
Baikunstha Nayak , aged about 61 years ,
S/o – Late Chakradhar Nayak ,
Vill / P.O – Itamati ,
P.S/ Dist : - Nayagarh .
————— Complainant .
- Vrs -
1. The Executive Engineer(A.G.M)
Elect. Division , CESU,At/P.O./P.S./Dist:- Nayagarh
2. The S.D.O.,(AMC) Electrical sub-Division, CESU
At/PO: Itamati PS/ Dist:- Nayagarh
3. The Junior Engineer(CESU) Elect. sub-Division, CESU
At/PO: Itamati PS/ Dist:- Nayagarh
—————- Opp . Parties .
Counsel for the complainant : - Sri K.C.Sahoo, ( Advocate )
Counsel for the O.Ps : - Sri R.K.Sahoo, ( Advocate )
Date of appearance of O.Ps : – 20-04-2009
Date of hearing : - 08-06-2009
Date of Judgment : – 30-06-2009
J U D G M E N T
P. K. Pattanaik , President :-
Deficiency in service on the part of the O. Ps is the grievance of the complainant .
The complainant’s case in brief is as follows : -
The complainant is a consumer under the O.Ps having Consumer No. D-16B028/000 and New A/C No. 03197049 . The meter status is O.K but the O.Ps have been whimsically and arbitrarily imposing bills on average basis since 2004 . The complainant has been paying the electricity dues regularly .But the O.Ps issued a bill in which the present arrear is shown as Rs.15,560/- . The O.Ps are demanding 30% of the total arrear dues i.e ,about Rs.4500/- from the complainant and are threatening to disconnect power supply unless the said 30% amount is paid . The complainant approached the O.Ps for the revision and correction of the said bill. The O.Ps assured him to revise and correct the arrear bill but the O.Ps have taken no steps till date to revise and correct the arrear bill .As per the complainant the O.Ps have not performed their duty in the proper manner and as such the O.Ps are guilty of deficiency in service for which the complainant has undergone harassment and mental agony
. According to the complainant the cause of action arose on 12.2.09 and 21.3.09 when the O.Ps issued the arrear bills and on 30.3.09 when the complainant expressed his inability to pay 30% of the total arrear dues .
The complainant has approached this Forum with a prayer to direct the O.Ps to pay him Rs.10,000/- towards deficiency in service and Rs.5,000/- towards litigation expenses, to direct to O.Ps for the revision and correction of the arrear bill from 2004 till date and not to demand 30% of the total arrear amount of Rs.15,560/- which is shown in the bill for March, 2009.
The complaint petition is not supported by affidavit but the complainant has filed xerox copies of electric bills for the month of February and March, 2009 and xerox copy of money receipt dt. 28.2.09 and these Xerox copies are marked as Annexure-1 to Annexure-3.
The O.Ps have filed written version in which it has been averred that the case is not maintainable. The O.Ps have averred that the statements contained in the complainant petition are partly correct. The complainant has not filed any document before the O.Ps to revise and correct the arrear dues till date. If the complainant will submit the relevant documents, then the O.Ps will try to revise and correct the arrear bill. As per the version of the O.Ps there is no deficiency on their part in providing service to the complainant and as such the case against them needs to be dismissed with cost.
The written version of the O. Ps is supported by affidavit.
On the pleadings of the parties , we take up the issue of deficiency in service for adjudication .
F I N D I N G S
Section (2) (1) (g) of the C.P ACT defines “Deficiency” as under :-
“Deficiency means any fault,imperfection,shortcoming or inadequacy
in the quality,nature and manner of performance which is required to be
maintained by or under any law for the time being in force or has been
undertaken to be performed by a person in pursuance of contract or
otherwise in relation to any service ”.
The complainant has alleged that he has been paying the electricity dues regularly but the bill for the month of February shows an arrear amount of Rs.15,487/- and the bill for month of March, 2009 shows the arrear amount as Rs.15,560 /- The complainant has been paying the electricity dues regularly and as such approached the O.Ps to correct and revise the said arrear bills,. The O.Ps assured him to revise and correct the arrear bill . But instead of revising and correcting the arrear bill, the O.Ps are demanding 30% of the total arrear dues and are threatening to disconnect power supply if the complainant will not deposit 30% of the total arrear dues. Such type of activity of the O.ps has put the complainant in harassment and mental agony and as such the O.Ps are guilty of deficiency in service.
The complainant has filed Xerox copy of the electricity bills and money receipt which are marked as Annexure-1 to Annexure-3.
Annexure -1 relates to the electricity bill for the month of March,2009 in which the amount due is shown as as Rs.15,560/-.
Annexure-2 relates to the electricity bill for February,09 in which amount due is shown as Rs.15,487/-.
Annexure-3 relates to the money receipt dt. 28.2.09 for Rs.400/-.
The O.ps have averred in their written version that the statements made in the complaint petition are partly correct. The O.ps have not mentioned as to which part of the complaint petition is correct and which part is not correct . They have not denied that the complainant has approached them for the revision and correction of the arrear bill.
In the light of the aforesaid analysis we are of the opinion that the O.Ps have not taken any action for the correction and revision of the disputed bill for which we hold that the O.Ps are guilty of deficiency in service.
Hence it is ordered .
O R D E R
The complainant’s case is partly allowed on contest against the O. Ps. The O. Ps are directed to correct and revise the arrear bill of the complainant and to provide a revised bill to the complainant . The complainant is also directed to provide the relevant documents to the O. Ps for the said correction and revision of the arrear bill. The O. Ps shall carry out this order within two months from the date of communication of this order. No order as to cost.
Sri P. K. Pattanaik
President .
Sri Pravakar Mishra Smt. Binodini Devi
Member Member