MUGNEERAM BANGUR & CO. Vs. SARDAR GURBACHAN SINGH

PETITIONER:
MUGNEERAM BANGUR & CO.

Vs.

RESPONDENT:
SARDAR GURBACHAN SINGH

DATE OF JUDGMENT:
16/12/1964

BENCH:
MUDHOLKAR, J.R.
BENCH:
MUDHOLKAR, J.R.
WANCHOO, K.N.

CITATION:
1965 AIR 1523          1965 SCR  (2) 630


ACT:
Contract  Act,    s. 56-Contract to purchase  plot-Subject  to
completion  of    development  work-Government  requisitioning
land-Rendering     completion   temporarily   unlawful-Whether
contract discharged.

HEADNOTE:
In May 1941, the respondent had entered into a contract with
the appellant company for the purchase of a plot of land  in
a  Colony  Scheme.  He had paid the earnest  money  and     had
undertaken to complete the transaction within on month    from
the  date of completion of certain development work  by     the
appellant.    Thereafter,   the      land     in   question     was
requisitioned  by the Government under the Defence of  India
Rules and the company was therefore unable to undertake     the
development work during the continuance of the war.
On  learning that the Government proposed to  de-requisition
the  lands taken over by them, in May 1946,  the  respondent
approached  the company to ascertain when it would  complete
development work after the de-requisitioning of the land, so
that  he  might complete the transaction  within  one  month
thereafter.   The  company claimed that the  contract  stood
cancelled since the respondent had failed to comply with the
terms  of a circular letter issued by it in  December  1943,
offering  all purchasers an option between accepting  refund
of   the  earnest  money  or  completing   the     transaction
immediately  by accepting the land in an undeveloped  state.
The  respondent denied having received the  circular  letter
and  filed a suit in August 1946, which was decreed  by     the
trial  court and the decree was upheld by the High Court  in
appeal.
In  the     Supreme  Court it was contended on  behalf  of     the
company     that  the  contract was  discharged  by  reason  of
frustration because its performance was rendered unlawful as
a   result  of    the  requisitioning  orders  made   by     the
Government, and furthermore, that the suit for specific per-
formance  was  premature,, because, under the  contract     the
respondent did not get the right to obtain a sale deed    till
after the development work was complete.
HELD   :  (i)  It  cannot  be  said  that  because  of     the
requisitioning    orders    which had the effect of     making     the
entry  by or on behalf of the company on the  land  illegal,
during the subsistence of the period of requisitioning,     the
contract stood discharged by frustration. [637 H]
If  time is of the essence of the contract, or if  the    time
for the performance is set out in the contract, the contract
would stand discharged even though its performance may    have
been  rendered unlawful for an indeterminate time,  provided
unlawfulness  attached to the performance at the  time    when
the contract ought to have been performed. [637 A-C]
In  the present case, it could not be said that time was  of
the  essence of the contract or that the contract  had    been
discharged because it had not been performed in a reasonable
time within the meaning of s. 46 of the Contract Act.    When
the  parties  entered  into  the  contract,  they  knew     the
prevailing  circumstances  and must have borne in  mind     the
possibility  of     difficulties  in  obtaining  the  necessary
material or the possibility of the land being  requisitioned
by the Government. [637 E-H]
631
Denny  Mott  & Dickson Ltd. v. James B. Frasser &  Co.    Ltd.
[1944]    A.C. 265 and Satyabrata Ghose and Ors. v.  Mugneeram
Bangur & Co. & Anr. [1954] S.C.R. 310. referred to.
(ii) The contention that the suit was premature could not be
accepted because    the development work had been  completed
when the appeal was heard by  the  High     Court.     In  such  a
case  the  court  would be justified  in  taking  notice  of
subsequent  events in moulding its relief accordingly.    [638
A-B]

JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 180 of 1962.
Appeal    by special leave from the judgment and decree  dated
January     28, 1959, of the Calcutta High Court from  original
Decree No. 226 of 1952.
B. Sen and S. N. Mukherjee, for the appellant.
Hem  Chandra  Dhar, S. S. Khanduja and Ganpat Rai,  for     the
respondent.
The Judgment of the Court was delivered by
Mudholkar, J. This appeal, like Satyabrata Ghose v.  Mugnee-
ram  Bangur  & Co. and another(1) relates to the  effect  of
requisitioning orders made by the Government during the last
war  under which they took possession of land  belonging  to
the  appellant company which had been divided into  building
plots  by  them in pursuance of what is known  as  the    Lake
Colony    Scheme,     by  constructing  roads  and  drains.     The
plaintiff-respondent was one of the various persons who     had
entered     into  contracts with the company  for    purchase  of
plots,    in  pursuance  of  the public  offers  made  by     the
company.  This he did by addressing the following letter  to
the company and paying Rs. 202/- by way of earnest money.
“To
Mugneeram Bangur and Company
Land Department.
Russa Road, South,
Tollygunge, Calcutta.
No. 499, Phone: South 135.
Through Babu-
Re : Plots Nos.     New Nos. 245 and 246 on 30 feet road in the
premises No. Lake Colony Scheme No. 1, Northern: Block.
Area measuring-10 ks. x ch. x sqr. ft more or less.
(1)  [1954] S.C.R. 310.
632
Dear Sir,
I am willing to purchase the above plot of land from you  at
the  average  rate of Rs. 1,075/- (Rupees one  thousand     and
seventyfive only) per katta irrespective of the condition of
the  soil and I am ready to deposit Rs. 202/- of the  actual
value as an earnest money at once.  I undertake to  complete
the  transaction within one month from the date     on(?)    (of)
completion  of    road  on  payment  of  the  balance  of     the
consideration  money and time must be deemed as     essence  of
the contract.  If I fail to do so within the said period the
earnest money deposited by me will be forfeited and you will
be  free  to resell the land and I shall be liable  for     all
damages     that  may result thereby.  I also agree to  sign  a
formal    agreement  in  the form required by you     if  you  so
desire.
Yours faithfully,
Name, Gurbachan Singh,
Address:  48/ 1, Chakraberia Road, North.
Dated the       19 ….
Witness : (Illegible)
Address ………………
N.B.  I agree to pay half of the value at     the
time  of    registration of the  deeds  and     the
balance within 6 years bearing interest at the
rate of 6 per cent per annum with half  yearly
rests  and  the said plots Nos : 245  and     246
purchased     by me shall remain charged for     the
payment  of the balance of the purchase  money
in  manner  as  aforesaid     and  the  necessary
security    deed charged should be executed     and
registered by me at my own cost.
Name:    Gurbachan Singh
Address  :
Witness  (Illegible)
4, Baktiar Shah Road, Tollygunge.
The  letter  does  not bear any date; but  probably  it     was
written     on  May  14, 1941 which is the date  on  which     the
company issued a receipt in his favour.     Different  portions
of  the     land covered by the scheme  were  requisitioned  by
Government between November 12, 1941 and July 25, 1944.     The
plots  which the respondents had contracted to purchase     are
said  to  form part of the land which was  requisitioned  by
virtue    of an order made by the Government on  February     18,
1944.
633
According  to the company, on December 24, 1943, a  circular
notice    was sent to all those persons who had  entered    into
contracts  for    purchase of plots from them stating  that  a
considerable  portion  of  the land comprised  in  the    Lake
Colony Scheme area had been requisitioned under the  Defence
of  India  Rules  and  was  taken  into     possession  by     the
Government.   It  was  not  possible to     say  how  long     the
Government   would  continue  to  be  in   possession    and,
therefore,  it was not possible for the company to carry  on
the work of the construction of roads and drains during     the
continuance  of     the war and possibly for  many     years    even
after  the  termination     of  the  war.     The  circular    then
proceeded to state as follows :-
“In  these  circumstances we have     decided  to
treat the agreement as cancelled and give     you
the  option  of taking of the  refund  of     the
earnest  money  deposited by  you     within     one
month from the receipt of this letter.
In  the    event of your refusal to  treat     the
contract as cancelled, we are offering you, in
the alternative, to complete the    registration
of the conveyance of the sale deed within     one
month  from  the receipt of this    letter.      In
such  a case you have to take the lands as  it
is now, the road and drain will be made by  us
as soon as circumstance will permit after     the
termination of the War.
If  you do not exercise your option in any  of
the  two    ways mentioned above  the  agreement
will be deemed to have been cancelled and your
earnest money forfeited.”
On  May     8, 1946 the respondent’s  attorneys,  acting  under
instructions,    wrote  to  the    company     saying      that     the
respondent  had     learnt from the company’s office  that     the
government  would be de-requisitioning lands taken  over  by
them  and  inquiring of the company as to when it  would  be
possible for the company to deliver possession of the  plots
to  the     respondent.  In reply to that    letter    the  company
wrote  on  May    29,  1946 drawing  his    attention  to  their
circular  letter and said that by reason of the     failure  of
the respondent to exercise the options given by them therein
the agreement stood cancelled and the earnest money had been
forfeited.
On June 13, 1946, the respondent’s attorneys expressed    sur-
prise at the company’s reply and stated that the  respondent
had  not received the circular referred to in the  company’s
reply and ended by saying as follows :
“That  my said client, therefore,     now  hereby
asks you as to when you are going to  complete
the  roads, so that he may do the needful     for
completion of the conveyances
634
within one month from such date of  completion
of the roads.
That  my said client hereby calls upon you  to
intimate    to him within seven days  from    date
the expected exact date of completion of roads
to  enable him to complete the  conveyance  as
per agreement, failing which he will be forced
to take legal steps against you in the  matter
as  he may be advised in the  matter,  without
further reference which please note.”
Apparently the company did nothing with the result that     the
present     suit was instituted by the respondent on August  8,
1946  in  the  court  of the  Second  Subordinate  Judge  at
Alipore.   The company resisted the suit on various  grounds
but  only  two are material for the purpose of    this  appeal
because     Mr.  Sen has confined his argument  only  to  those
matters.   One is that the contract has been  discharged  by
reason    of frustration and the second is that the  suit     was
premature.  The suit was decreed and that decree was  upheld
by  the High Court in appeal.  A certificate that  the    case
was fit for appeal to this Court having been refused by     the
High  Court the company sought and obtained from this  court
special     leave to appeal.  That is how the matter  comes  up
before us.
This case would really appear to be covered by the  decision
of this court to which we have referred at the outset.     Mr.
Sen, however, points out that the question as to whether the
contract  could be said to have been discharged     because  of
the  fact  that its performance was rendered unlawful  as  a
result    of the requisitioning orders made by the  Government
which was sought to be raised before this Court in that case
was not permitted to be raised by it and has been left open.
He  admits  that  certain observations made  by     this  Court
towards     the  concluding  portion  of  the  judgment   would
indicate that this Court was not prepared to accept the con-
tention     sought     to be urged before it.     But, Mr.  Sen    says
that  as the contention was not permitted to be raised,     the
observations  of this Court could be said to have been    made
merely    in  passing and at best be regarded as    a  tentative
expression  of its views.  We think Mr. Sen is right in     the
sense that the question has been actually left open by    this
Court.     But even so, we will have to consider    whether     the
grounds upon which the previous decision rests would not  be
relevant  for consideration in connection with the  argument
advanced by Mr. Sen.
635
In so far as discharge of contract by reason of     frustration
is concerned there is no question of implying a term in     the
contract a term fundamental for its performance, as is    done
by the courts in England because we have here the provisions
of  s.    56 as well as those of s. 32 of     the  Contract    Act.
This is what was held by this Court in the earlier case     and
that  decision    binds  us.   No doubt,    a  contract  can  be
frustrated  either because of supervening  impossibility  of
performance  or because performance has become    unlawful  by
reason of circumstances for which neither of the parties was
responsible.   In the earlier case this Court has held    that
where  the  performance     of an essential  condition  of     the
contract   has     become     impossible   due   to     supervening
circumstances the contract would be discharged.     This  Court
has  further  held  that the impossibility need     not  be  an
absolute  one  but it is sufficient if    further     performance
becomes impracticable by some cause for which neither of the
parties     was responsible.  It, however, held that  the    mere
fact  that  the     performance of an  essential  term  of     the
contract  that is to say, of undertaking development of     the
area  under the scheme could not be undertaken    because     the
land  had  been requisitioned, did not have  the  effect  of
frustrating  the  contract.  For though the  term  regarding
development  was  an  essential term of     the  contract,     the
requisitioning of the land was only for a temporary  period.
Further     the  parties had deliberately not placed  any    time
limit  within  which  roads  and  drains  had  to  be    made
apparently  because they were aware of the  difficulties  in
carrying on the work on account of scarcity of materials and
the various restrictions which the Government had placed  on
such activities.  This Court also pointed out:
“Another important thing that requires  notice
in this connection is that the war was already
on,   when  the  parties    entered      into     the
contract.       Requisition    orders    for   taking
temporary possession of lands for war purposes
were  normal events during this period.”    (pp.
326-327).
Though    these observations were made while dealing with     the
argument that the contract has been frustrated by reason  of
impossibility of performance they would not be wholly out of
place  while considering the argument based upon the  ground
that continued performance of the contract had been rendered
unlawful.
What s. 56 speaks of is a contract, the performance of which
has become unlawful.  Now, it is true that no order was made
under  the  Defence of India Rules prohibiting    the  company
from  carrying    on  the work of construction  of  roads     and
drains.     The
636
actual    order served upon the company, among  other  things,
provides :
“The owner/occupier of the said land:
(a)   shall   place  the    said  land  at     the
disposal and under the control of the Military
Estates Officer Bengal Circle on and from     the
14th  November,  1941 at 1  P.M.    Bengal    time
until six months after the termination of     the
present war unless relinquished earlier.”
In consequence of this order the company lost possession  of
the  land  and automatically lost access  thereto.   Without
getting     on to the land the company could not carry out     its
obligation  to the purchasers of constructing the roads     and
drains.      If, in disobedience of this order,  the  company’s
servants, agents or contractors were to carry on the work of
construction of the roads and drains by entering on the land
of which the possession was with the government, they  would
have been liable to punishment under sub r. (7) of r. 75 (a)
of the Defence of India Rules and also the company.  We were
informed  that    the  land was used  by    the  Government     for
military purposes.  It is, therefore, possible that the land
might have been declared as a protected place under r. 7  of
the  Defence of India Rules.  Even, however, without such  a
declaration,  we agree with Mr. Sen that it would  not    have
been  possible    for  the company, its  agents,    servants  or
contractors  to     go on the land during    the  continuance  in
force  of  the order of requisition without  being  rendered
liable at law.
Even so it is clear that all that had become unlawful was to
construct  roads and drains while the land was bound  to  be
given up by the Government sometime or other and, therefore,
in essence the activities which were rendered unlawful    were
not forbidden for all time but only temporarily.  It may  be
that  the  duration  of the embargo was     uncertain  but     not
permanent.   It     would, therefore, be  relevant     to  enquire
whether     a contract could properly be held to be  frustrated
because     for  a certain period of time its  performance     has
become unlawful.  According to Mr. Sen the moment it  became
unlawful for one of the parties to the contract to  continue
with  the  performance, the contract was discharged  and  in
this  connection he referred us to certain  observations  of
Lord Wright in Denny Mott & Diskson Ltd. v. james B.  Fraser
& Co. Ltd.,() and certain other portions of the report.      We
put to him the question as to what would be the. effect of a
requisitioning, say, for a period of one month.     Would    that
operate as &charge of the
(1)  [1944] A.C. 265, 274.
637
contract  ?  To that his answer was in the negative  and  we
think that the answer was right.  The question then would be
: would it make any difference if unlawfulness would  attach
to  the     performance of the contract  for  an  indeterminate
period    ? In our judgment if time is of the essence  of     the
contract  or  if  time for performance is  set    out  in     the
contract it may be that the contract would stand  discharged
even though its performance may have been rendered  unlawful
for an indeterminate time provided unlawfulness attached  to
the  performance  of  the  contract at    the  time  when     the
contract  ought     to have been performed.   Thus,  where     the
performance  of     a contract had been  rendered    unlawful  by
reason    of  some subsequent event the contract    would  stand
discharged   but   such     discharge  will  take     place     not
necessarily  from the date on which the further     performance
was  rendered  unlawful,  unless  further  performance     was
rendered  unlawful for all time.  If the performance of     the
contract  is  rendered    unlawful either     for  a     determinate
period    of time or for an indeterminate period of  time     the
contract  would not stand discharged unless the ban  on     its
performance  existed on the day or during the time in  which
it  has to be performed.  Here it is pointed out by Mr.     Sen
that  the  respondent  had  made time  the  essence  of     the
contract  but that only applies to the grant  of  conveyance
after  the completion of the roads and drains.     As  already
pointed     out,  parties    were wholly silent as  to  the    time
within    which  the roads and drains were  to  be  completed.
Therefore,  in    so  far as this aspect of  the    contract  is
concerned  time     was  in no sense made the  essence  of     the
contract.  According to Mr. Sen, however, where the  parties
have failed to specify in the contract time within which  it
has  to be performed s. 46 of the Contract Act comes in     and
the parties may be presumed to have agreed that the contract
will  be  performed  within reasonable time.   To  that     the
answer would-be the same as that given in the earlier  case,
that  is, the parties when they entered into  the  contract,
knew the prevailing circumstances and must have home in mind
the  possibility that something like what actually  happened
may  happen and, therefore, did not specify the time  within
which  the  land had to be developed.  In other     words,     the
parties      intended  to    exclude     from  the  computation      of
reasonable  time such time as was taken up in procuring     the
necessary material which was not easy to obtain and such  as
may   be  taken     up  if     the  land  were  requisitioned      by
government.   Thus,  in     our view it  cannot  be  said    that
because of the requisitioning orders which had the effect of
making the entry by or on behalf of the company on the    land
illegal      during   the     subsistence  of   the     period      of
requisitioning the contract stood discharged.
p.55-7
638
Then remains the other point argued by Mr. Sen. He said that
the  suit  for specific performance  was  premature  because
under  the agreement the respondent did not get a  right  to
obtain    a sale deed till after the development of  the    land
comprised  in the scheme was completed.     That  is  perfectly
true.    But  the  fact    remains     that  this  work  had    been
completed when the appeal was heard by the High Court.     The
Court would in such a case be justified in taking notice  of
subsequent events in moulding its relief accordingly.
In our judgment the courts below were right in upholding the
respondent’s claim.  The apeal is dismissed with costs.
Appeal dismissed.
639

PETITIONER:
MUGNEERAM BANGUR & CO.

Vs.

RESPONDENT:
SARDAR GURBACHAN SINGH

DATE OF JUDGMENT:
16/12/1964

BENCH:
MUDHOLKAR, J.R.
BENCH:
MUDHOLKAR, J.R.
WANCHOO, K.N.

CITATION:
1965 AIR 1523          1965 SCR  (2) 630

ACT:
Contract  Act,    s. 56-Contract to purchase  plot-Subject  to
completion  of    development  work-Government  requisitioning
land-Rendering     completion   temporarily   unlawful-Whether
contract discharged.

HEADNOTE:
In May 1941, the respondent had entered into a contract with
the appellant company for the purchase of a plot of land  in
a  Colony  Scheme.  He had paid the earnest  money  and     had
undertaken to complete the transaction within on month    from
the  date of completion of certain development work  by     the
appellant.    Thereafter,   the      land     in   question     was
requisitioned  by the Government under the Defence of  India
Rules and the company was therefore unable to undertake     the
development work during the continuance of the war.
On  learning that the Government proposed to  de-requisition
the  lands taken over by them, in May 1946,  the  respondent
approached  the company to ascertain when it would  complete
development work after the de-requisitioning of the land, so
that  he  might complete the transaction  within  one  month
thereafter.   The  company claimed that the  contract  stood
cancelled since the respondent had failed to comply with the
terms  of a circular letter issued by it in  December  1943,
offering  all purchasers an option between accepting  refund
of   the  earnest  money  or  completing   the     transaction
immediately  by accepting the land in an undeveloped  state.
The  respondent denied having received the  circular  letter
and  filed a suit in August 1946, which was decreed  by     the
trial  court and the decree was upheld by the High Court  in
appeal.
In  the     Supreme  Court it was contended on  behalf  of     the
company     that  the  contract was  discharged  by  reason  of
frustration because its performance was rendered unlawful as
a   result  of    the  requisitioning  orders  made   by     the
Government, and furthermore, that the suit for specific per-
formance  was  premature,, because, under the  contract     the
respondent did not get the right to obtain a sale deed    till
after the development work was complete.
HELD   :  (i)  It  cannot  be  said  that  because  of     the
requisitioning    orders    which had the effect of     making     the
entry  by or on behalf of the company on the  land  illegal,
during the subsistence of the period of requisitioning,     the
contract stood discharged by frustration. [637 H]
If  time is of the essence of the contract, or if  the    time
for the performance is set out in the contract, the contract
would stand discharged even though its performance may    have
been  rendered unlawful for an indeterminate time,  provided
unlawfulness  attached to the performance at the  time    when
the contract ought to have been performed. [637 A-C]
In  the present case, it could not be said that time was  of
the  essence of the contract or that the contract  had    been
discharged because it had not been performed in a reasonable
time within the meaning of s. 46 of the Contract Act.    When
the  parties  entered  into  the  contract,  they  knew     the
prevailing  circumstances  and must have borne in  mind     the
possibility  of     difficulties  in  obtaining  the  necessary
material or the possibility of the land being  requisitioned
by the Government. [637 E-H]
631
Denny  Mott  & Dickson Ltd. v. James B. Frasser &  Co.    Ltd.
[1944]    A.C. 265 and Satyabrata Ghose and Ors. v.  Mugneeram
Bangur & Co. & Anr. [1954] S.C.R. 310. referred to.
(ii) The contention that the suit was premature could not be
accepted because    the development work had been  completed
when the appeal was heard by  the  High     Court.     In  such  a
case  the  court  would be justified  in  taking  notice  of
subsequent  events in moulding its relief accordingly.    [638
A-B]

JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 180 of 1962.
Appeal    by special leave from the judgment and decree  dated
January     28, 1959, of the Calcutta High Court from  original
Decree No. 226 of 1952.
B. Sen and S. N. Mukherjee, for the appellant.
Hem  Chandra  Dhar, S. S. Khanduja and Ganpat Rai,  for     the
respondent.
The Judgment of the Court was delivered by
Mudholkar, J. This appeal, like Satyabrata Ghose v.  Mugnee-
ram  Bangur  & Co. and another(1) relates to the  effect  of
requisitioning orders made by the Government during the last
war  under which they took possession of land  belonging  to
the  appellant company which had been divided into  building
plots  by  them in pursuance of what is known  as  the    Lake
Colony    Scheme,     by  constructing  roads  and  drains.     The
plaintiff-respondent was one of the various persons who     had
entered     into  contracts with the company  for    purchase  of
plots,    in  pursuance  of  the public  offers  made  by     the
company.  This he did by addressing the following letter  to
the company and paying Rs. 202/- by way of earnest money.
“To
Mugneeram Bangur and Company
Land Department.
Russa Road, South,
Tollygunge, Calcutta.
No. 499, Phone: South 135.
Through Babu-
Re : Plots Nos.     New Nos. 245 and 246 on 30 feet road in the
premises No. Lake Colony Scheme No. 1, Northern: Block.
Area measuring-10 ks. x ch. x sqr. ft more or less.
(1)  [1954] S.C.R. 310.
632
Dear Sir,
I am willing to purchase the above plot of land from you  at
the  average  rate of Rs. 1,075/- (Rupees one  thousand     and
seventyfive only) per katta irrespective of the condition of
the  soil and I am ready to deposit Rs. 202/- of the  actual
value as an earnest money at once.  I undertake to  complete
the  transaction within one month from the date     on(?)    (of)
completion  of    road  on  payment  of  the  balance  of     the
consideration  money and time must be deemed as     essence  of
the contract.  If I fail to do so within the said period the
earnest money deposited by me will be forfeited and you will
be  free  to resell the land and I shall be liable  for     all
damages     that  may result thereby.  I also agree to  sign  a
formal    agreement  in  the form required by you     if  you  so
desire.
Yours faithfully,
Name, Gurbachan Singh,
Address:  48/ 1, Chakraberia Road, North.
Dated the       19 ….
Witness : (Illegible)
Address ………………
N.B.  I agree to pay half of the value at     the
time  of    registration of the  deeds  and     the
balance within 6 years bearing interest at the
rate of 6 per cent per annum with half  yearly
rests  and  the said plots Nos : 245  and     246
purchased     by me shall remain charged for     the
payment  of the balance of the purchase  money
in  manner  as  aforesaid     and  the  necessary
security    deed charged should be executed     and
registered by me at my own cost.
Name:    Gurbachan Singh
Address  :
Witness  (Illegible)
4, Baktiar Shah Road, Tollygunge.
The  letter  does  not bear any date; but  probably  it     was
written     on  May  14, 1941 which is the date  on  which     the
company issued a receipt in his favour.     Different  portions
of  the     land covered by the scheme  were  requisitioned  by
Government between November 12, 1941 and July 25, 1944.     The
plots  which the respondents had contracted to purchase     are
said  to  form part of the land which was  requisitioned  by
virtue    of an order made by the Government on  February     18,
1944.
633
According  to the company, on December 24, 1943, a  circular
notice    was sent to all those persons who had  entered    into
contracts  for    purchase of plots from them stating  that  a
considerable  portion  of  the land comprised  in  the    Lake
Colony Scheme area had been requisitioned under the  Defence
of  India  Rules  and  was  taken  into     possession  by     the
Government.   It  was  not  possible to     say  how  long     the
Government   would  continue  to  be  in   possession    and,
therefore,  it was not possible for the company to carry  on
the work of the construction of roads and drains during     the
continuance  of     the war and possibly for  many     years    even
after  the  termination     of  the  war.     The  circular    then
proceeded to state as follows :-
“In  these  circumstances we have     decided  to
treat the agreement as cancelled and give     you
the  option  of taking of the  refund  of     the
earnest  money  deposited by  you     within     one
month from the receipt of this letter.
In  the    event of your refusal to  treat     the
contract as cancelled, we are offering you, in
the alternative, to complete the    registration
of the conveyance of the sale deed within     one
month  from  the receipt of this    letter.      In
such  a case you have to take the lands as  it
is now, the road and drain will be made by  us
as soon as circumstance will permit after     the
termination of the War.
If  you do not exercise your option in any  of
the  two    ways mentioned above  the  agreement
will be deemed to have been cancelled and your
earnest money forfeited.”
On  May     8, 1946 the respondent’s  attorneys,  acting  under
instructions,    wrote  to  the    company     saying      that     the
respondent  had     learnt from the company’s office  that     the
government  would be de-requisitioning lands taken  over  by
them  and  inquiring of the company as to when it  would  be
possible for the company to deliver possession of the  plots
to  the     respondent.  In reply to that    letter    the  company
wrote  on  May    29,  1946 drawing  his    attention  to  their
circular  letter and said that by reason of the     failure  of
the respondent to exercise the options given by them therein
the agreement stood cancelled and the earnest money had been
forfeited.
On June 13, 1946, the respondent’s attorneys expressed    sur-
prise at the company’s reply and stated that the  respondent
had  not received the circular referred to in the  company’s
reply and ended by saying as follows :
“That  my said client, therefore,     now  hereby
asks you as to when you are going to  complete
the  roads, so that he may do the needful     for
completion of the conveyances
634
within one month from such date of  completion
of the roads.
That  my said client hereby calls upon you  to
intimate    to him within seven days  from    date
the expected exact date of completion of roads
to  enable him to complete the  conveyance  as
per agreement, failing which he will be forced
to take legal steps against you in the  matter
as  he may be advised in the  matter,  without
further reference which please note.”
Apparently the company did nothing with the result that     the
present     suit was instituted by the respondent on August  8,
1946  in  the  court  of the  Second  Subordinate  Judge  at
Alipore.   The company resisted the suit on various  grounds
but  only  two are material for the purpose of    this  appeal
because     Mr.  Sen has confined his argument  only  to  those
matters.   One is that the contract has been  discharged  by
reason    of frustration and the second is that the  suit     was
premature.  The suit was decreed and that decree was  upheld
by  the High Court in appeal.  A certificate that  the    case
was fit for appeal to this Court having been refused by     the
High  Court the company sought and obtained from this  court
special     leave to appeal.  That is how the matter  comes  up
before us.
This case would really appear to be covered by the  decision
of this court to which we have referred at the outset.     Mr.
Sen, however, points out that the question as to whether the
contract  could be said to have been discharged     because  of
the  fact  that its performance was rendered unlawful  as  a
result    of the requisitioning orders made by the  Government
which was sought to be raised before this Court in that case
was not permitted to be raised by it and has been left open.
He  admits  that  certain observations made  by     this  Court
towards     the  concluding  portion  of  the  judgment   would
indicate that this Court was not prepared to accept the con-
tention     sought     to be urged before it.     But, Mr.  Sen    says
that  as the contention was not permitted to be raised,     the
observations  of this Court could be said to have been    made
merely    in  passing and at best be regarded as    a  tentative
expression  of its views.  We think Mr. Sen is right in     the
sense that the question has been actually left open by    this
Court.     But even so, we will have to consider    whether     the
grounds upon which the previous decision rests would not  be
relevant  for consideration in connection with the  argument
advanced by Mr. Sen.
635
In so far as discharge of contract by reason of     frustration
is concerned there is no question of implying a term in     the
contract a term fundamental for its performance, as is    done
by the courts in England because we have here the provisions
of  s.    56 as well as those of s. 32 of     the  Contract    Act.
This is what was held by this Court in the earlier case     and
that  decision    binds  us.   No doubt,    a  contract  can  be
frustrated  either because of supervening  impossibility  of
performance  or because performance has become    unlawful  by
reason of circumstances for which neither of the parties was
responsible.   In the earlier case this Court has held    that
where  the  performance     of an essential  condition  of     the
contract   has     become     impossible   due   to     supervening
circumstances the contract would be discharged.     This  Court
has  further  held  that the impossibility need     not  be  an
absolute  one  but it is sufficient if    further     performance
becomes impracticable by some cause for which neither of the
parties     was responsible.  It, however, held that  the    mere
fact  that  the     performance of an  essential  term  of     the
contract  that is to say, of undertaking development of     the
area  under the scheme could not be undertaken    because     the
land  had  been requisitioned, did not have  the  effect  of
frustrating  the  contract.  For though the  term  regarding
development  was  an  essential term of     the  contract,     the
requisitioning of the land was only for a temporary  period.
Further     the  parties had deliberately not placed  any    time
limit  within  which  roads  and  drains  had  to  be    made
apparently  because they were aware of the  difficulties  in
carrying on the work on account of scarcity of materials and
the various restrictions which the Government had placed  on
such activities.  This Court also pointed out:
“Another important thing that requires  notice
in this connection is that the war was already
on,   when  the  parties    entered      into     the
contract.       Requisition    orders    for   taking
temporary possession of lands for war purposes
were  normal events during this period.”    (pp.
326-327).
Though    these observations were made while dealing with     the
argument that the contract has been frustrated by reason  of
impossibility of performance they would not be wholly out of
place  while considering the argument based upon the  ground
that continued performance of the contract had been rendered
unlawful.
What s. 56 speaks of is a contract, the performance of which
has become unlawful.  Now, it is true that no order was made
under  the  Defence of India Rules prohibiting    the  company
from  carrying    on  the work of construction  of  roads     and
drains.     The
636
actual    order served upon the company, among  other  things,
provides :
“The owner/occupier of the said land:
(a)   shall   place  the    said  land  at     the
disposal and under the control of the Military
Estates Officer Bengal Circle on and from     the
14th  November,  1941 at 1  P.M.    Bengal    time
until six months after the termination of     the
present war unless relinquished earlier.”
In consequence of this order the company lost possession  of
the  land  and automatically lost access  thereto.   Without
getting     on to the land the company could not carry out     its
obligation  to the purchasers of constructing the roads     and
drains.      If, in disobedience of this order,  the  company’s
servants, agents or contractors were to carry on the work of
construction of the roads and drains by entering on the land
of which the possession was with the government, they  would
have been liable to punishment under sub r. (7) of r. 75 (a)
of the Defence of India Rules and also the company.  We were
informed  that    the  land was used  by    the  Government     for
military purposes.  It is, therefore, possible that the land
might have been declared as a protected place under r. 7  of
the  Defence of India Rules.  Even, however, without such  a
declaration,  we agree with Mr. Sen that it would  not    have
been  possible    for  the company, its  agents,    servants  or
contractors  to     go on the land during    the  continuance  in
force  of  the order of requisition without  being  rendered
liable at law.
Even so it is clear that all that had become unlawful was to
construct  roads and drains while the land was bound  to  be
given up by the Government sometime or other and, therefore,
in essence the activities which were rendered unlawful    were
not forbidden for all time but only temporarily.  It may  be
that  the  duration  of the embargo was     uncertain  but     not
permanent.   It     would, therefore, be  relevant     to  enquire
whether     a contract could properly be held to be  frustrated
because     for  a certain period of time its  performance     has
become unlawful.  According to Mr. Sen the moment it  became
unlawful for one of the parties to the contract to  continue
with  the  performance, the contract was discharged  and  in
this  connection he referred us to certain  observations  of
Lord Wright in Denny Mott & Diskson Ltd. v. james B.  Fraser
& Co. Ltd.,() and certain other portions of the report.      We
put to him the question as to what would be the. effect of a
requisitioning, say, for a period of one month.     Would    that
operate as &charge of the
(1)  [1944] A.C. 265, 274.
637
contract  ?  To that his answer was in the negative  and  we
think that the answer was right.  The question then would be
: would it make any difference if unlawfulness would  attach
to  the     performance of the contract  for  an  indeterminate
period    ? In our judgment if time is of the essence  of     the
contract  or  if  time for performance is  set    out  in     the
contract it may be that the contract would stand  discharged
even though its performance may have been rendered  unlawful
for an indeterminate time provided unlawfulness attached  to
the  performance  of  the  contract at    the  time  when     the
contract  ought     to have been performed.   Thus,  where     the
performance  of     a contract had been  rendered    unlawful  by
reason    of  some subsequent event the contract    would  stand
discharged   but   such     discharge  will  take     place     not
necessarily  from the date on which the further     performance
was  rendered  unlawful,  unless  further  performance     was
rendered  unlawful for all time.  If the performance of     the
contract  is  rendered    unlawful either     for  a     determinate
period    of time or for an indeterminate period of  time     the
contract  would not stand discharged unless the ban  on     its
performance  existed on the day or during the time in  which
it  has to be performed.  Here it is pointed out by Mr.     Sen
that  the  respondent  had  made time  the  essence  of     the
contract  but that only applies to the grant  of  conveyance
after  the completion of the roads and drains.     As  already
pointed     out,  parties    were wholly silent as  to  the    time
within    which  the roads and drains were  to  be  completed.
Therefore,  in    so  far as this aspect of  the    contract  is
concerned  time     was  in no sense made the  essence  of     the
contract.  According to Mr. Sen, however, where the  parties
have failed to specify in the contract time within which  it
has  to be performed s. 46 of the Contract Act comes in     and
the parties may be presumed to have agreed that the contract
will  be  performed  within reasonable time.   To  that     the
answer would-be the same as that given in the earlier  case,
that  is, the parties when they entered into  the  contract,
knew the prevailing circumstances and must have home in mind
the  possibility that something like what actually  happened
may  happen and, therefore, did not specify the time  within
which  the  land had to be developed.  In other     words,     the
parties      intended  to    exclude     from  the  computation      of
reasonable  time such time as was taken up in procuring     the
necessary material which was not easy to obtain and such  as
may   be  taken     up  if     the  land  were  requisitioned      by
government.   Thus,  in     our view it  cannot  be  said    that
because of the requisitioning orders which had the effect of
making the entry by or on behalf of the company on the    land
illegal      during   the     subsistence  of   the     period      of
requisitioning the contract stood discharged.
p.55-7
638
Then remains the other point argued by Mr. Sen. He said that
the  suit  for specific performance  was  premature  because
under  the agreement the respondent did not get a  right  to
obtain    a sale deed till after the development of  the    land
comprised  in the scheme was completed.     That  is  perfectly
true.    But  the  fact    remains     that  this  work  had    been
completed when the appeal was heard by the High Court.     The
Court would in such a case be justified in taking notice  of
subsequent events in moulding its relief accordingly.
In our judgment the courts below were right in upholding the
respondent’s claim.  The apeal is dismissed with costs.
Appeal dismissed.
639

Leave a Reply