Archive for April, 1994

G. RAMACHANDRA REDDY Vs. CHIEF ENGINEER

Friday, April 29th, 1994

PETITIONER:
G. RAMACHANDRA REDDY

Vs.

RESPONDENT:
CHIEF ENGINEER

DATE OF JUDGMENT29/04/1994

BENCH:
RAMASWAMY, K.
BENCH:
RAMASWAMY, K.
VENKATACHALA N. (J)

CITATION:
1994 AIR 2381          1994 SCC  (5) 142
JT 1994 (4)   181      1994 SCALE  (2)1057

ACT:

HEADNOTE:

JUDGMENT:
ORDER
1.   Leave granted.
2.   This  appeal arises from the judgment of the Division  Bench
of Madras High Court in OSA No. 281 of 1992 dated 5-1-1993.
3.The  appellant’s contract was terminated by  the  respondent
and in consequence thereof, by notices dated 23-7-1991 and  21-8-
1991,  the  appellants exercising the option under clause  17  of
General Condition of Contract, called upon the    Engineer-in-Chief
to  appoint  sole  Arbitrator,    in  terms  of  the  contract,  to
adjudicate  the dispute that had arisen between them.    Since  no
action    was taken by the respondents, the appellant filed a  suit
on  43-1992  under Section 20 of the Arbitration  Act,    1940  for
short  ‘the Act’, requesting the Court to appoint an  arbitrator.
Learned     Single     Judge of the High Court by  his  judgment  dated
23-9-1992 appointed Justice M.A. Sattar Syeed, a retired Judge of
the  High Court as sole Arbitrator.  On appeal, a Division  Bench
of that High Court agreed with the Single Judge that despite  the
issue  of  notice  calling upon the  respondent     to  appoint  the
Arbitrator  in terms of the contract, no action was taken by  the
respondent.   Its suggestion that the respondent could agree  for
appointment of any one of the five arbitrators named in the  list
given  by the appellant did not find favour with the  respondent.
Yet,  the  Division Bench directed the respondent to  appoint  an
arbitrator  within  15 days from that date and declared     that  in
case the respondent failed to do so, the arbitrator appointed  by
the  Single  Judge would be deemed to have been     appointed  under
Section     20.   The  appellant,    feeling     aggrieved  against   the
judgment of the Division Bench, has filed the appeal.
4.Shri K. Parasaran, learned Senior Counsel for the  appellant
contended  that     once  the appellant had  issued  notice  to  the
respondent calling upon him to appoint an arbitrator in terms  of
the  contract,    the  failure  to do so had  given  right  to  the
appellant  to  invoke the jurisdiction of the civil  court  under
Section     20(4)    of  the Act and that court  got     jurisdiction  to
appoint     the Arbitrator of its choice.    When the  learned  Single
Judge  had exercised its jurisdiction under Section 20(4) of  the
Act and appointed the arbitrator, the Division Bench committed    a
manifest error of law in interfering with that appointment.  Shri
A.S.  Nambiar,    the learned Senior Counsel  for     the  respondent,
sought    to support the Division Bench judgment relying    upon  the
judgment  of  this  Court in Union of  India  v.  Prafulla  Kumar
Sanyal1 wherein this Court had observed that before appointing an
arbitrator  by the court itself “it is desirable that  the  court
should    consider  the  feasibility of  appointing  an  arbitrator
according  to the terms of the contract” and the issuance of  the
notice giving 15 days’ time as contemplated under Section 8(a) of
the  Act  did  not  arise  on the  facts  in  the  present  case.
Therefore,  his     contention was that though  the  appellant  (sic
respondent) had not appointed the arbitrator before the expiry of
15  days’  notice before the matter was decided by  the     Division
Bench the appellant was given an option to accept
1   (1979) 3 SCC 631
145
anyone    among the five named persons to be a sole Arbitrator  and
having    failed to accept anyone, it is not open to the    appellant
to  impugn the correctness of legality of the appointment of  the
Arbitrator by the Division Bench, in terms of the contract,
5.We  find no force in the contentions of Shri Nambiar.      This
Court  interpreting  Section 20(4) of the Act, has,  in     Prafulla
Kumar  case’ itself, specifically laid down that sub-section  (4)
requires “that the court shall make an order of reference to  the
arbitrator  appointed  by  the parties    under  the  agreement  or
otherwise  if  such arbitrator had not been  appointed    when  the
parties     cannot     agree to appoint an arbitrator,  the  Court  may
proceed     to appoint an arbitrator by itself’.  In that case,  the
parties     agreed before this Court, expressing their  desire  that
the  President    should    be  asked to  appoint  an  arbitrator  as
contemplated  under clause 29 within two months from the date  of
the order passed by this Court.     In that backdrop this Court  had
expressed  the    desirability  or the feasibility  to  appoint  an
arbitrator in terms of the contract.  Those observations of  this
Court  cannot  be understood or torn out of context and     read  in
isolation.   The court should endeavour that the contract  should
always    be  given  effect to, though the  contracting  party  had
failed    to act according to contract.  It is to be seen,  whether
the contract provided for the appointment of a named  arbitrator,
and  if so, the parties normally would be bound by the    terms  of
contract  and  the court would not be justified     to  appoint  any
arbitrator  unless the arbitrator refused or neglected    to  enter
upon the reference, etc.  In the absence of any named  arbitrator
it  would  be  open to the contracting parties to  agree  for  an
appointment  of     an  arbitrator     by  agreement    even  after   the
proceedings  were laid in the Court under Section 20 of the  Act.
In the absence of any such agreement, the Court gets jurisdiction
and  power to appoint an arbitrator.  In Prafulla Kumar case’  no
notice    was  given to the appellant to appoint an  arbitrator  in
terms of the contract before the suit was filed and no action was
taken  pending suit except contending that the matter  was  under
active    consideration.    In that context, it was held that in  the
absence     of  any  agreement, the  court     gets  jurisdiction.   In
Nandyal Co-op.    Spinning Mills Ltd. v. K. V. Mohan Rao2 15  days’
notice    was given to the respondent to act upon the terms of  the
contract to appoint an arbitrator, but it was not done,     although
it  was stated that the matter was under consideration,     It  was,
therefore, held thus: (SCC pp. 660-6 1, para II)
“It  would thus be clear that if no arbitrator  had
been  appointed in terms of the contract within  15
days  from the date of receipt of the  notice,  the
administrative head of the appellant had    abdicated
himself  of the power to appoint    arbitrator  under
the  contract.   The  court  gets     jurisdiction  to
appoint  an arbitrator in place of the contract  by
operation  of  Section 8(1)(a).  The  contenti
on  of
Shri  Rao,  therefore,  that  since  the    agreement
postulated  preference to arbitrator  appointed  by
the administrative head of the appellant and if  he
neglects    to appoint, the only remedy open  to  the
contractor was to have recourse to civil suit is
2 (1993) 2 SCC 654
146
without force.  It is seen that under the     contract
the respondent contracted out from adjudication of.
his  claim  by  a civil court.   Had  the     contract
provided for appointment of a named arbitrator  and
the  named person was not appointed, certainly  the
only  remedy left to the contracting party was  the
right to suit.  That is not the case on hand.   The
contract     did  not  expressly  provide    for   the
appointment  of a named arbitrator.  Instead  power
has  been given to the administrative head  of  the
appellant     to  appoint sole  arbitrator.     When  he
failed to do so within the stipulated period of  15
days  enjoined  under  Section  8(1)(a),    then  the
respondent  has been given right under clause  65.2
to  avail     the  remedy under  Section  8(1)(a)  and
request the court to appoint an arbitrator.  If the
contention  of  Shri Rao is  given  acceptance,  it
would  amount  to     putting a  premium  on     inaction
depriving      the    contractor  of    the   remedy   of
arbitration frustrating the contract itself.”
6.Thus    when the notice was given to the opposite  contracting
party to appoint an arbitrator in terms of the contract and if no
action had been taken, it must be deemed that he neglected to act
upon  the contract.  When no agreement was reached, even  in  the
court between the parties, the court gets jurisdiction and  power
to  appoint an arbitrator.  Even if Section 8(a) per se does  not
apply, notice was an intimation to the opposite contracting party
to  act upon the terms of the contract and his/its  non-availment
entails     the forfeiture of the power to appoint an arbitrator  in
terms  of  the    contract and gives right to the     other    party  to
invoke the court’s jurisdiction under Section 20. In the  instant
case  the  respondent did not appoint an  arbitrator,  after  the
notice    was  received.     The respondent averred     in  the  written
statement  that     it  was under consideration.    Even  before  the
learned Single Judge he did not even state that he was willing to
appoint      an  arbitrator.   The     learned  Single  Judge      rightly
exercised the power under Section 20(4) of the Act and    appointed
the Arbitrator.     The Division Bench, therefore, was not right  in
holding that the appellant has by giving option to the respondent
to  agree for appointment of an arbitrator out of the five  named
persons     had left it to the respondent to appoint  an  arbitrator
and  allowing respondent to appoint an arbitrator.  On the  other
hand, the appointment of an arbitrator made by the learned Single
Judge must be deemed to have been approved by us.
7.The  appeal  is accordingly allowed.    The  judgment  of  the
Division Bench is set aside and that of the learned Single  Judge
is restored.  In the circumstances, parties are directed to  bear
their own costs.
147